The Diary Game||Date: 03 November 2026||Final day of work at the 132 kV high-voltage substation.
Steemian Friends,
Today, I will write my diary entry for November 3, 2026. Through this entry, I will share with you the various activities I engaged in throughout the day. I hope you all enjoy reading my diary.

My Thumbnail Photo(Special joint for 33 kV high-voltage cable)
Today, as I do every day, I woke up in the morning and logged into my account on the Steemit platform. I then upvoted some posts by other authors. At 7:00 AM, I took a bath and got ready to head to the office, even though my official start time is 10:00 AM. Due to a fire that broke out at the 132 kV electrical substation a week ago, the power supply to several units has been interrupted. I am hopeful that it will be possible to restore power to all the units today. Upon arriving at the office, I had my breakfast. Afterward, I went to the 132 kV electrical substation and began my work. We organized ourselves into three separate teams to carry out the tasks.

132 KV Electrical Control Room
The workload is somewhat lighter today, as most electrical units are already operational. A high-voltage cable jointing team has arrived and begun their work. A specialized procedure is employed for making joints in high-voltage lines. To facilitate this, a Megger meter was used to identify the specific cables; it is crucial to correctly distinguish between the red, black, and yellow cables. If the cables are misidentified, fans in the load section will rotate in the reverse direction.
Every high-voltage cable is currently energized, which means we are working under risky conditions today. Each of our teams is carrying out their tasks with extreme precision. Meanwhile, due to two transformers being out of service, power load-shedding is currently in effect. Once one of the transformers is brought back online this afternoon, the load-shedding will decrease. The load-shedding is being managed from the electrical control room.

Special joint for 33 kV high-voltage cable
This is the most significant electrical fault I have encountered in my professional career. The damage was most severe in the transformer’s control systems and high-voltage cables, which were destroyed by fire. Nevertheless, after nearly ten days, most of the units at the electrical substation have now been brought back into operation. Following lunch, I returned my focus to my work.
My YouTube Link
In the afternoon, it was officially decided that power supply would be restored to all units tomorrow at 10:00 AM. Consequently, I left the electrical substation in the evening and headed home. On my way, I enjoyed some delicious street food—even though such food is not exactly hygienic. For the first time in about ten days, I finally feel free from mental stress.
After returning home in the evening, I take some time to rest. Then, I begin writing a blog post for the Steemit platform. In addition to keeping a personal diary, I compile and submit a post titled "Active Contest List." Writing this blog takes me about three hours. Although I feel quite exhausted after a full day of work at the office, I am very happy that I am still able to write these posts. Finally, at 11:30 PM, I have dinner and go to sleep.






This is my X share link :
https://x.com/mahadih83660186/status/2119058269700489666?a=mpBb5Eg9Ub-QWoMS1n4&s=19
Working with energized high voltage cables sounds pretty intense. Glad you finally got some relief from the stress after ten long days.
Qué laburo el de los cables rojo, negro y amarillo con el Megger, fijate que si se cruzan los tenés girando al revés. En casa siempre les digo a los chicos que el orden importa, aunque sea para conectar un ventilador. ¿Diez días para levantar todo después del incendio fue el promedio o se les complicó más de lo previsto?